SAP’s Project System with SAP ERP 6.0 EHP4 certification as a profession has an incredible evolution over the last few years. SAP C_TPLM22_64 Project System with SAP ERP 6.0 EHP4 exam is the forerunner in validating credentials against. Here are updated SAP C_TPLM22_64 exam questions, which will help you to test the quality features of DumpsSchool exam preparation material completely free. You can purchase the full product once you are satisfied with the product.

Question: 1

How can material components be assigned to network activities?
Note: There are three (3) correct answers to this question.

A. By assigning them manually
B. Using the bill of materials transfer
C. Using assigned sales orders
D. Using ProMan
E. Using the Internet-based catalog

Answer: ABE

Question: 2

You want to confirm working hours to a WBS element using Cross Application Time Sheet (CATS). However, once you enter the WBS element and the working hours in CATS you receive an error message. What could be the reason?
Please choose the correct answer.

A. The system status created is active.
B. The system status master data locked is activate.
C. You are not the responsible person for that WBS element.
D. The confirmation exceeds the budget assigned to the WBS.

Answer: A

Question: 3

You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?
Please choose the correct answer.
A. Bottom-up
B. Strict bottom-up
C. Free planning
D. Top-down

Answer: A

Question: 4

You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use?
Please choose the correct answer.
A. Standard time scheduling
B. Standard Bill of Material (BOM)
C. Standard cost planning
D. Standard Milestones

Answer: D

Question: 5

Your projects consist of WBS elements, several networks, and subnetworks. What are the advantages of new overall network scheduling (CN24N) instead of the old overall network scheduling (CN24)?
Note: There are three (3) correct answers to this question.

A. Scheduling of subnetworks and subordinate internal orders
B. Introduction of a configurable level concept for the targeted selection of subnetworks
C. Scheduling that takes available capacities and material availability into account
D. Improve performance through the targeted selection of subnetworks to be scheduled.
E. Detailed subnetwork monitor

Answer: BDE