SAP C_TFIN22_67 Exam Preparation Questions For Best Result – Updated 2018

If you are in the hunt for an SAP C_TFIN22_67 exam dumps material that will bring you closer to success, 640-864.org is here to provide help in Management Accounting (CO) with SAP ERP 6.0 EhP6 C_TFIN22_67 certification exam. For several years now, we are the leading provider of C_TFIN22_67 exam questions for Management Accounting (CO) with SAP ERP 6.0 EhP6 Cost Center Accounting, Internal Orders, Product Cost Planning C_TFIN22_67 Exam. we have served over 70,000 IT professionals and helped them achieve their goals.

C_TFIN22_67 exam questions, C_TFIN22_67 PDF dumps; C_TFIN22_67 exam dumps:: https://www.dumpsschool.com/C_TFIN22_67-exam-dumps.html (300 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TFIN22_67 Dumps Exam Questions and Answers:

Version: 4.0
Question: 21

A customer wants to allocate the over absorption/under absorption of cost centers source related to receiver. What is the most accurate allocation rule?
Please choose the correct answer.
Response:

A. Assessment of fixed portions based on any value field of the market segments.
B. Assessment of posted amounts based on any value field of the market segments.
C. Assessment of posted amounts based on any derivation rule of characteristics.
D. Assessment of fixed portions based on statistical key figures of the market segment.

Answer: B

Question: 22

A customer wants to settle an internal order to cost centers, but receives an error message. What do you check?
Please choose the correct answer.
Response:

A. The system and the user status.
B. The sender and receiver to be assigned to the same profit center.
C. The PA transfer structure of the order.
D. The costing sheet.

Answer: A

Question: 23

New Updated C_TFIN22_67 Exam Questions C_TFIN22_67 PDF dumps C_TFIN22_67 practice exam dumps: https://www.dumpsschool.com/C_TFIN22_67-exam-dumps.html

Which of the following organizational units are maintained in Management Accounting?
There are 2 correct answers to this question.
Response:

A. Controlling area
B. Operating concern
C. Company code
D. Business area
E. Functional area

Answer: AB

Question: 24

Which planning transactions debit receivers with secondary cost elements?
There are 2 correct answers to this question.
Response:

A. Transfer of depreciations from Asset Accounting
B. Activity input planning
C. Transfer of personnel costs from SAP HCM
D. Plan assessment

Answer: BD

Question: 25

Which of the following statements are correct?
Please choose the correct answer
Response:

A. Cost center can default in all FI line items in all GL accounts
B. Internal order can default in all FI line items in all GL accounts
C. The cost center can default in GL accounts provided it is assigned to company code.
D. The cost center is linked to company code as Chart of accounts is linked to the same company code.

Answer: C

Question: 26

The characteristic of tangible goods is stated below. Which of the following statement not correct?
Please choose the correct answer.
Response:

A. Materials can be produced in-house, subcontracted or procured externally.
B. Product object. the cost estimate can also be used for comparison purpose in cost controlling
C. No inventory exists.
D. The product cost planning is used to arrive at the cost estimate for the same.

Answer: C